top of page

SINGAPORE

Marina one

COMPLETED 2018

Engaged by Specialist Steel Sub-contractor, as alternative design PE to convert the structural systems of 2 office towers from concrete to steel in collaboration with Magnusson Klemencic Associates, USA.·

 

QP for High-rise Glass Lift, Cantilevered Signature Restaurants, and Bubble lift Steel Structures.

The office towers are 210m tall with large floor plates (3,500m2 avg) and floor beams of up to 21m in span. The building profile is vertically sloped and horizontally curved, demanding inclined columns at various changing angles.

Construction Sequence Analysis to mitigate movements in the office tower during construction and provide alternative design for a convoluted curved pedestrian ramp from steel to rc.

GET IN TOUCH:

KK Lim & Associates Pte Ltd

Tel: +65 6377 0036

Email: contactus@kklim.com.sg

5 Jln Kilang Barat #07-03

Petro Centre 
Singapore 159349

© 2019 by KKLim & Associates.

CONTACT US:

Thanks for submitting!

bottom of page